RMC or Site Mixed Concrete: What Actually Costs You More

On most sites in Surat the argument stops at the rate per cubic metre. Site mixed concrete looks cheaper on that one number, so it wins the conversation. The number that matters is what the finished structure costs once cement wastage, labour, storage, rework and schedule slippage are added back in.

Two ways to batch the same M25

The difference is not the ingredients. It is whether anyone knows how much of each went in.
Site mixed
  • Cement counted in bags
  • Sand and aggregate measured by farma, filled by eye
  • Water added by the operator's judgement
  • Aggregate moisture not measured, not corrected
  • Record of the batch none
Ready mix
  • Cement weighed to the mix design
  • Sand and aggregate weighed on load cells
  • Water dosed to a fixed water cement ratio
  • Aggregate moisture tested, water corrected each batch
  • Record of the batch printed slip with every load

Where site mixing loses control

Site mixing batches by volume. Cement goes in by the bag, sand and aggregate go in by farma, and the water goes in by the operator’s judgement. Aggregate moisture changes through the day and nobody adjusts for it, so the water cement ratio moves pour to pour. That variation is why nominal mixes are permitted only up to M20 under IS 456. Anything above that needs a design mix, and a design mix needs weigh batching to mean anything.

The cement you cannot see on the bill

Most site gangs quietly add extra cement as insurance against that variation. Five to ten percent over the design requirement is common. On a 500 cubic metre project that is several hundred bags bought only to cover a batching problem. RMC removes the guesswork, so the cement content stays where the mix design put it.

Speed changes the whole schedule

A site mixer with a full labour gang manages roughly 5 to 8 cubic metres a day. A transit mixer and pump place 30 to 60 cubic metres an hour. A slab that takes four days of site mixing, with cold joints at every stoppage, becomes one continuous monolithic pour. Shuttering comes off sooner, the next floor starts sooner, and the interest on the project clock stops running.

Side by side

Parameter Site mixed concrete Ready mix concrete
Batching By volume, using farma or head pan. Cement bags counted, sand and aggregate estimated by eye By weight, computer controlled batching plant with printed batch record for every load
Water control Water added by judgement of the mixer operator, changes through the day Water cement ratio fixed in the design mix and held to it, corrected for aggregate moisture
Achievable grade Nominal mixes are permitted only up to M20 under IS 456 Design mixes from M20 to M60 with trial mix backing
Output Roughly 5 to 8 cubic metres a day with a site mixer and labour gang 30 to 60 cubic metres an hour with a boom or line pump
Cement usage Usually 5 to 10 percent extra cement is added as a safety margin against variation Cement content fixed by the mix design, no padding needed
Site impact Needs storage space, water point, labour, and creates dust and spillage No storage, no stacking, no gang on site, minimal cleanup
Records Rarely documented, hard to defend during audit Batch slip and cube test reports for every pour
Best suited to Small repairs, plinth work, remote sites, quantities under about 3 cubic metres Slabs, columns, rafts, roads and any pour where strength has to be proven

The quote shows one line. The pour costs five.

What site mixing adds to the delivered cost of a cubic metre.

Breakdown of hidden costs added by site mixed concrete beyond the quoted rate per cubic metre

When site mixing is still the right call

Small repairs, plinth beams, boundary walls, remote pockets where a mixer cannot reach, and anything under about three cubic metres. Below that volume the mobilisation does not justify a transit mixer. Above it, and certainly on any load bearing element, RMC is the cheaper decision once the full cost is counted.

Frequently asked questions

1. Is RMC actually more expensive than site mixed concrete?

The rate per cubic metre is higher. The delivered cost is usually lower once you account for the extra cement added as a safety margin, the labour gang, storage space, spillage, and the days saved on the schedule. Compare cost per finished slab, not cost per cubic metre.

2. What is the minimum quantity PM RMC will supply?

A standard transit mixer carries 6 cubic metres. Smaller loads can be arranged, though the cost per cubic metre rises because the mobilisation is the same. Talk to our team about part loads for smaller pours.

3. How long can concrete stay in the transit mixer?

Placement should be completed within about 90 minutes of batching in normal conditions, and sooner in peak summer. Plan the pour so the mixer is not waiting at the gate, because that clock starts at the plant, not at your site.

4. Can water be added at site if the concrete looks stiff?

No. Retempering with water raises the water cement ratio and drops the strength permanently. If workability is a problem, the fix is a plasticiser dosed at the plant or on delivery under supervision, not a hosepipe.

5. Can RMC be used for a small residential building?

Yes, and it is common for slab pours in individual houses in and around Surat. The usual constraints are site access for the transit mixer and a clear approach for the pump boom. Both can be planned a week ahead.

6. One supplier across the pour

PM Group supplies the ready mix, the aggregate that goes into it, and the paver blocks that finish the surface above it. Nearly thirty years of supply into South Gujarat, one delivery schedule, one point of accountability. Send us your grade, quantity and pour date, and we will confirm the mix design and the slot.